NOTES
- WBS – output from scope definition, Input 4 : scope verification/control, activity definition, resource planning, cost estimating, cost budgeting, risk mgmt plan
- For Integrated/Scope/Schedule/Cost change control, the INPUT always’ve: Performance Reports, Change request, ‘some’ plans to process eg. Scope mgmt plan, ‘some’ inputs from other ‘output’ before eg. WBS,project schedule, Project plan,cost baseline , TOOLS & TECH always’ve Performance measurement, additional planning, ‘some’control system , OUTPUTS always’ve Corrective Action, Lesson Learned ,’some’ changes eg. Scope changes/proj.plan updates/Revised cost estimates/Budget updates .
- Scope Initiation – INPUT: Historical info;
- Scope Planning – INPUT:Constraint & Assumption,
- Scope Definition: Historical info+ Constraint & Assumptions
- EQUAL Activity Definition = Activity Duration Estimating,
- NOTICE ques. of planning/estimating usually have HIST.INFO ->Resource Planning, Cost Estimating, Risk Identification, Quantitative Risk Analysis OR CONSTRAINTS & ASSUMPTIONS ->Comm.Planning, Schedule Development, Procurement Planning
- OUTPUT of a PLAN usually INPUT to ALL of the internal processes eg.
- a) PIM – output Proj.plan development: Project Plan (INPUT)->Proj.plan execution & Integrated Change Control
- b) Quality – quality mgmt plan(INPUT)->Quality Assurance, Quality Control
- c) HR – staffing mgmt plan (INPUT) ->staff acquisition, team development
- d) RISK – Risk mgmt plan (INPUT)->Risk qualitative analysis,Risk quantitative analysis,Risk Response Planning, Risk Monitoring & Control
- EXCEPTION : (a) Scope Mgmt plan (INPUT)-> Scope change Control; Output from Scope Planning ; (b) Schedule Mgmt plan (INPUT)-> Schedule Control; Output from Schedule Development ; (c) Cost Mgmt Plan (INPUT)->Cost Control; Output from Cost Estimating ; (d) Communication Mgmt Plan (INPUT)->Information Distribution; Output from Communications Planning ; (e) Procurement Mgmt Plan(INPUT)-> Solicitation Planning; Output from Procurement Planning
- EVM only exists in Project Plan Development & Cost Control
- Product Description only exists in Scope Initiation, Scope Planning ,Activity Sequencing,Quality Planning, Procurement Planning
- Administrative Closure INPUT: Product documentation, Performance Measurement documentation,other project reports, OUTPUT Project archives,Closure, Lesson Learned;(TOOLS & TECH: Project reports/ presentations, Performance Reporting T&T)
- Contract Closure INPUT: Contract Documentation, OUTPUT Formal Acceptance & Closure (TOOTS & TECH: Procurement Audit)
- Scope Verification INPUT: Product documentation,Work Results,Proj.plan,
- Scope statement, WBS, (T&T : Inspection) & OUTPUT: Formal Acceptance
- ACTIVITY LIST input to Activity Sequencing & Activity Duration Estimating, BUT Schedule Development INPUT: Proj.Network Diagrams, Activity Duration Estimates, Risk Mgmt Plan , Also Identified Risk->Activity Duration Estimating
- ACTIVITY DURATION ESTIMATES input to Resource Planning, Cost Estimating BUT Cost Budgeting INPUT Cost Estimates, Project Schedule, Risk Management Plan,WBS
- OPERATIONAL DEFINITIONS input to Quality Assurance, Quality Control
- Quality Assurance Input also QC measurements; quality mgmt plan , op
- Quality Control Input also Checklist,Work Result; quality mgmt plan, op
- QC OUTPUT: Quality Improvement,Acceptance Decision,Completed Checklist, Process Adjustment, Rework
- Work Results, Project Plan are INPUT to Infor. Distribution, Perf. Reporting
- Team Development INPUT: Project Staff, Project Plan, Performance Reports, External Feedback, Staffing Mgmt Plan
- Performance Reporting T&T: Performance Review, Trend/Variance/Earn Value Analysis, Info Distribution T&T:Comm.Skills, Info.Retrieval sys,Info Distribution methods
- Identified Risk is INPUT: Qualitative Risk & Quantitative Risk
- Risk Mgmt planning INPUT: Proj.Charter, risk mgmt policies, WBS, Templates to risk mgmt plan;
- Risk Qualitative INPUT: Project Status, Project Type;
- Risk Quantitative INPUT: Historical Info , Expect Judgment;
- Risk Response Planning INPUT: Probabilistic analysis of the project, Probability of achieving time & cost objectives, list of potential responses, risk thresholds,risk owners ,common risk causes,
- Risk Monitoring & control INPUT: Project Communication, Scope changes
- Those connected are Overall risk ranking,List of prioritized risk, Trends result in qualitative; List of quantified risk, Trends Result in Qualitative (quality), ALL this INPUT to risk response planning
- Risk Monitoring & Control INPUT: Additional risk identification & analysis , (T&T): Additional Risk Response Planning, (OUTPUT): Updates to Risk response plan, Risk DB, Risk Identification Checklists, also workaround plans, corrective action , project change requests
- T&T for Procurement Planning: Make-Buy Analysis, Expert Judgment, Contract
- Type Selection; Solicitation Planning: Expert Judgment, Standard Forms
- Those Connected are SOW->Procurement Doc->Qualified Seller List->Bidding->Proposals->Evaluation Criteria/Organ.Policies->Contract Negotiation/Weighting system->Contract->Contract Administration
- Contract Administration INPUT: Contract, Work Results, Change Request, Seller Invoices, T&T: Contract change control, Performance Reporting, Payment System, OUTPUTS: Correspondence, Contract Changes, Payment Requests
- Scope Statement INPUT: Scope Definition, Scope Verification,Activity definition,Resource Planning, Quality Planning, Procurement Planning
- Work Result(OUTPUT from Project Plan Execution) INPUT TO: Scope Verification,Quality Control,Information Distribution, Performance Reporting,Contract Administration
- PM Software T&T: Schedule Development, Schedule Control,Resource Planning
| Ads Column |
Print This Post
|




You can contribute blog posts by registering yourself as a user, 



0 responses so far ↓
There are no comments yet...Kick things off by filling out the form below.
Leave a Comment