What to Study?
(Be familiar with Inputs, Tools and Techniques, and Outputs for each phase)
Activity: An element of work
performed during the course of a project.
(Normally has duration, cost, and resource requirements.)
Baseline: The original plan plus or minus approved changes.
Arrow Diagram Method (ADM): A network
diagramming technique in which activities are represented
by arrows. The tail of the arrow represents the start and
the head of the
arrow represents the end of the activity. Activities are
connected at
points called nodes to illustrate the sequence in which
activites are
expected to be performed. Also called Activity-On-Arrow
(AOA).
Backward Pass: The calculation of
late finish and start dates for the uncompleted portions
of all network activities. Determined by working
backwards through the
network logic from the project's end date.
Concurrent Engineering: Generally speaking, an approach to project staffing that calls for the
implementors to be involved in the design phase. (sometimes confused with fast tracking.)
Crashing: Taking action to decrease the total project duration after analyzing a
number of alternatives to determine how to get the maximum duration compression for the least cost.
Critical Activity: An activity on a critical path.
Critical Path: The series of activities which determines the earliest completion of the
project. The critical path is usally defined as those activities with float
less than or equal to a specified value (usually zero).
Critical Path Method (CPM): A network analysis technique used to predict project duration by
analyzing which path has the least amount of scheduling flexibility.
Early dates are calculated using a forward pass; late dates are
calculated using a backwards pass.
Data Date (DD): The point in time that separates actual (historical) data from future
(scheduled) data. Also called as-of date.
Dummy Activity: An activity of zero duration used to show a logical relationship in the
arrow diagramming method. Dummy activities are used when logical
relationships cannot be completely or correctly described with regular
activity arrows. Dummies are shown graphically as a dashed line
headed by an arrow.
Duration (DU): The number of work periods (not including holidays and other non-working periods) required to complete an activity or other project element.
Early Finish Date (EF): In the critical path method, the earliest possible date in which the
uncompleted portions of an activity or project can complete. Can
change as the project progresses.
Early Start Date (ES): In the critical path method, the earliest possible date in which the
uncompleted portions of an activity or project can start Can change
as the project progresses.
Effort: The number of labor units required to complete an activity or other
project element. Should not be confused with duration.
Event-on-Node: A network diagramming technique in which events are represented by
boxes (or nodes) connected by arrows to show the sequence in which
the events are to occur.
Fast Tracking: Compressing the project schedule by overlapping activities that would
normally be done in sequence (such as design and construction).
Float: The amount of time that an activity may be delayed from its early
start without delaying the project finish date. (Also called slack, total
float, and path float).
Forward Pass: The calculation of the early start and early finish dates for the
uncompleted portions of all network activities.
Free Float (FF): The amount of time an activity can be delayed without delaying the
early start of any immediately succeeding activities.
Gantt Chart: A graphic display of schedule-related information using bars.
Hammock: An aggregate or summary activity.
Hanger: An unintended break in a network path. Hangers are usually caused by
missing activities or missing logical relationships.
Lag: A modification of a logical relationship which directs a delay in the successor task.
Late Finish Date (LF): In the critical path method, the latest possible date that an activity may be completed without delaying a specified milestone (usually the project finish date).
Late Start Date (SF): In the critical path method, the latest possible date that an activity may
begin without delaying a specified milestone (usually the project finish date).
Lead: A modification of a logical relationship which allows an acceleration of
the successor task. For example, in a FS relationship with a 10 day
lead, the successor can start 10 days prior to the completion of the
predecessor.
Level of Effort (LOE): Support type activity (e.g., vendor or customer liason) that does not
readily lend itself to measurement of discrete accomplishment.
Generally characterized by a uniform rate of activity over a specific period of time.
Logical Relationship: A dependency between two project activities or between an activity and
a milestone. Four possible types: FS, FF, SS, and SF. (see logical relationships under concepts).
Master Schedule: A summary level schedule which identifies the major activities and milestones.
Milestone: A significant event in the project, usually completion of a major
deliverable.
Milestone Schedule: A summary level schedule which identifies the major milestones.
Path Convergence: In mathematical analysis, the tendency of parallel paths of approximately
equal duration to delay the completion of the milestone where they
meet.
Precedence Diagram Method (PDM): A network diagramming technique in which activities are represented by nodes. Activities are linked by precedence relationships to show the
sequence in which the activiites are to be performed.
Program Evaluation and Review Technique (PERT): An event-oriented network analysis technique used to estimate project duration when there is a high degree of uncertainty with the individual
activity duration estimates.
Project Network Diagram: Any schematic display of the logical relationships of project activities.
Always drawn from left to right to reflect project chronology. Often incorrectly referred to as a "PERT chart".
Remaining Duration (RDU): The time needed to complete an activity.
Resource Leveling: Any form of network analysis in which start and finish dates are driven by resource management concerns.
Resource-Limited Schedule: A project schedule whose start and finish dates reflect expected
resource availability. The final project schedule should always be
resource limited.
Scheduled Finish Date (SF): The point in time work was scheduled to finish on an activity. The
scheduled finish date is normally within the range of dates delimited by
the early finish date and the late finish date.
Scheduled Start Date (SS): The point in time work was scheduled to start on an activity. The
scheduled start date is normally within the range of dates delimited by
the early start and late start dates.
Slack: Synonymous with float.
Time-Scaled Network Diagram: Any project network diagram drawn is such a way that the positioning
and length of the activity represents its duration. Essentially, it is a
bar chart that includes network logic.
Total Float: Synonymous with float.
Work Item: Synonymous with activity.
1. During what Time Management Process are the specific activities that must be performed to produce the deliverables in the WBS identified and documented?
2. A period of time in work weeks which includes non-working days is called:
3. The amount of time that an activity can be delayed from its early start without delaying the project end date is called:
4. What are you likely to see as a project progresses in a schedule with must fix dates and little or no slack?
5. Given the following estimates: Optimistic 3 days, Pessimistic 9 days, and most likely 6 days, what is the PERT weighted average?
6. What is the standard deviation for the estimates in the above problem?
7. In crashing the schedule, you would focus on:
8. To calculate the late start and late finish dates for a set of tasks, you must do:
9. An activity that consumes no time or resources and shows only that a dependency exists between two activities is called:
10. A modification of a logical relationship that allows an acceleration of the successor task is represented by:
11. Assuming a PERT weighted average computation, what is the probability of completing the project within plus-or-minus 3 standard deviations of the mean?
12. Schedule variance can be determined by:
13. What is critical path?
14. The Time Management Process that involves identifying and documenting interactivity dependencies is called:
15. A network diagram that uses nodes to represent activities and arrows to show the activity dependencies and allows no loops is called:
