Procurement Management

Reference Material to study:

What to Study?

(Be familiar with Inputs, Tools and Techniques, and Outputs for each phase)

Key Definitions

Back Charge: Cost of corrective action by purchaser and chargeable to the supplier under terms of the contract.

Bid Protest: allows an unsuccessful supplier an opportunity to protest the award of a government contract to another supplier.

Bill of Lading: A receipt issued by a carrier for merchandise to be delivered to a party at some destination.

Constructive change: occurs when the PM's conduct enables performance differing from that prescribed by the contract. The PM's conduct in effecting constructive change may either be affirmitive or a failure to act. Not part of change control of contract: For instance, if final product performs better than standard specified in contract, or if the PM increases the quality over and beyond what's stated in the contract.

Contract: a legal document of purchase or sale which is binding on both parties.

When entering into a contract, the people involved must have legal capacity to do so. (the definition of legal capacity varies from state to state). Consideration must be provided to both parties (in other words, there must be sufficient cause to contract). There must be mutual assent.

Invitation for Bid (IFB): PMBOK equates this with Request for Proposal and recognizes that it may have a more specific meaning in certain application areas. (appropriate for high dollar, standard items.)

Lowball: In order to get an award, a contractor may submit at bid that's unrealistically low.

Pink Team Review: A seller responds to an RFP by developing a proposal. For sanity purposes, the proposal is passed through the pink team once the outline is completed. The pink team looks at the outline through the perspective of the buyer. The purpose of the team is to catch problems with the proposal in the early stages.

Price Forecast: based on information gathered and analyzed about demand and supply. This forecast provides a prediction of short and long term prices and the underlying reasons for those trends.

Red Team Review: Once the proposal is in draft form, it passes through a red team which again looks at the proposal through the buyer's perspective.

Reformation: A judicial remedy by which a court interprets the contract so as to express the real intention of the parties (this is different from changes to the contract)

Request for Proposal (RFP): A type of bid document used to solicit proposals from prospective sellers of products or services. In some application areas, it may have a more specific meaning. (appropriate for high dollar, non-standard items).

Request for Quotation (RFQ): PMBOK does not distinguish between RFQ and RFP. However, PMBOK does recognize that some application areas have a more specific meaning for RFQ (appropriate for low dollar items such as supplies and materials).

Statement of Work (SOW): Describes the portion of the product to be contracted. In general, this is different from the product description (which tends to be more broader). Under the circumstance where the seller is producing the entire product, the distinction between SOW and the product description becomes moot. Government terms: SOW is reserved for a procurement item that is a clearly specified product or service, and Statement of Requirements (SOR) is used for procuring an item that is presented as a problem to be solved.

Project Procurement Management

Procurement Planning:

Solicitation Planning:

Solicitation:

Source Selection:

Contract Administration:

Contract Closeout:

Contract Origination

Two ways in which a contract can originate: unilaterally or bilaterally

Unilaterally:

Bilaterally:

Procurement documents are used to solicit proposals from prospective sellers. The procurement document then becomes the basis for the seller's proposal. The following are examples of procurement documents:

  1. Request for quotation (RFQ) from different suppliers
  2. Request for proposal (RFP):
  3. Invitation for bid (IFB):

Contract Types

Two principal types of contracts: cost and fixed

Unit Price:

Cost-Plus-Award-Fee (CPAF): (from the Frame Book)

The following contracts are ordered in increasing risk to the seller and decreasing risk to the buyer:

Cost-Plus-Percentage of Cost (CPPC):

Cost-Plus-Fixed Fee (CPFF):

Cost-Plus-Incentive Fee (CPIF):

Fixed Price-Plus-Incentive Fee (FPI):

Firm-Fixed Price (FFP):

Examples of Contract Types

CPPC:

 
Estimated cost: $1,000K Percentage: 10% ($100K)
Estimated total price: $1,100K (Estimated cost + 10%*Estimated cost)
   
If cost increases to $1,100K the total price would be $1,100K plus 10% of the actual costs = $1,210K.
   

CPFF:

 
Estimated cost: $1,000K Percentage: 10% ($100K)
Estimated total price: $1,100K (Estimated cost + 10%*Estimated cost)
   
If cost increases to $1,100K the total price would be $1,100K plus 10% of the original estimated costs = $1,200K.
   

CPIF:

 
Estimated cost: $1,000K Predetermined fee: $100K
   
Sharing formula: 85/15 (buyer absorbs 85% of the uncertainty and the seller absorbs 15% of the risk)
   
Actual cost: $800K Savings: $200K
Seller gets: $800K + $100K + $30K = $930K (Actual cost + Fee + 15%*Savings)
Buyer saves: $170K  
   

FPI:

 
Target cost: $1,000K Target profit: $100K (Seller's fee)
Target price: $1,100K Ceiling price: $1,200K (The maximum payout to the seller)
Share ratio: 70/30  
     
Example A: Actual cost: $800K Savings: $200K (Target cost - Actual cost)
  Seller gets: $800K + $100K + 60K = $960K (Actual cost + fee + 30%*savings)
  Buyer saves: $140K  
     
Example B: Actual cost: $1,300K  
  Seller gets: $1,200K (no profit and a $100K loss on costs)
  Buyer loses: $100K (the payout is $100K over Target price = Ceiling Price)

FFP: (Lump Sum)

     
Price: $1,000K  
   
Example A: Actual cost: $700K  
  Seller makes a profit of $300K (Price - Actual Cost)
     
Example B: Final cost $1,100K Seller loses $100K on contract
   

Contract Execution

Special Considerations

Changes:

Specifications:

Contract Execution

Special Considerations, cont.

Quality Control:

Warranties:

Analogy: If you buy a lawnmower, you would expect it to cut grass. If you use it on the carpet, the warranty doesn't apply.

Contract Execution

Special Considerations, cont.

Waiver:

Bonds:

Breaches:

Negotiation

Stages of Negotiation:

  1. Protocol: Introductions are made, and the negotiators get to know each other. The atmosphere for the rest of the negotiations is determined in this stage.
  2. Probing: The negotiators begin the search process. Each party identifies issues of concern. Strengths and weaknesses are identified and possible areas of interest.
  3. Scratch Bargaining: This is the essence of the meeting. Actual bargaining occurs and concessions are made. Points of concession are identified.
  4. Closure: The two positions are summed up and final concessions are reached. The agreements are summarized and documented.
  5. Agreement: The main difficulty in this stage is ensuring both parties have an identical understanding of the agreements. This stage should establish the plans for recording the agreements in a written contract.

Negotiation Tactics:

The PM should be aware of the following negotioation tactics.

Sample Questions


  1. A unilateral contract under which the seller is paid a preset amount per unit of service is called:
  1. A cost reimbursable contract
  2. A lump sum contract
  3. A unit price contract
  4. A fixed price contract
  5. b or d

2. Which of the following is considered during the Procurement Planning Process?

  1. Whether to procure
  2. How to procure and how much to procure
  3. What and when to procure
  4. b and c
  5. all of the above

3. From a buyer's standpoint, which of the following is true?

  1. Procurement planning should include consideration of potential subcontracts
  2. Procurement planning does not include consideration of potential subcontracts since this is the duty of the contractor.
  3. Subcontractors are first considered during the Solicitation Process
  4. none of the above

4. Which of the following processes involves obtaining information (bids and proposals) from prospective sellers?

  1. Procurement Planning
  2. Source Selection
  3. Contract Administration
  4. Solicitation
  5. Solicitation Planning

5. Which of the following is true about procurement documents?

  1. Procurement documents are used to solicit proposals from prospective sellers.
  2. Invitation for Bid and Request for Proposal are two examples of procurement documents.
  3. Procurement documents should be structured to facilitate accurate and complete responses from prospective sellers.
  4. b and c
  5. all of the above

6. Which of the following is a method for quantifying qualitative data in order to minimize the effect of personal prejudice on source selection?

  1. Weighting system
  2. Screening system
  3. Selecting system
  4. none of the above
  5. all of the above

7. Which of the following is true concerning evaluation criteria?

  1. Can often be found in procurement documents
  2. Can be objective or subjective
  3. Used to rate or score proposals
  4. May be limited to purchase price if procurement item is readily available from number of sources
  5. all of the above

8. Which of the following are inputs to the Source Selection Process?

  1. Evaluation criteria
  2. Organizational policies
  3. Procurement documents
  4. a and b
  5. all of the above

9. A significant difference between independent estimates and proposed pricing could mean that:

  1. The independent estimates are most likely incorrect and the proposed pricing correct
  2. The SOW was not adequate
  3. The prospective seller either misunderstood or failed to respond fully to the SOW.
  4. b or c
  5. a or c

10. Which of the following are examples of indirect costs?

  1. Salaries of corporate executives
  2. Salaries of full-time project staff
  3. Overhead costs
  4. a and b
  5. a and c

11. Which of the following contract types places the greatest risk on the seller?

  1. Cost-plus-fixed-fee contract
  2. Cost plus-incentive-fee contract
  3. Fixed-price-incentive contract
  4. Firm-fixed-price contract

12. In which of the following contract types is the seller's profit limited?

  1. Cost-plus-percentage-cost contract
  2. Cost-plus-fixed-fee contract
  3. Fixed-price-plus-incentive
  4. b and c
  5. none of the above

13. A cost-plus-percentage-cost (CPPC) contract has an estimated cost of $120,000 with an agreed profit of 10% of the costs. The actual cost of the project is $130,000.
What is the total reimbursement to the seller?

  1. $143,000
  2. $142,000
  3. $140,000
  4. $132,000

14. A cost-plus-incentive-fee (CPIF) contract has an estimated cost of $150,000 with a predetermined fee of $15,000 and a share ratio of 80/20. The actual costs of the project is $130,000. How much profit does the seller make?

  1. $31,000
  2. $19,000
  3. $15,000
  4. none of the above

15. A fixed-price-plus-incentive-fee (FPI) contract has a target cost of $130,000, a target profit of $15,000, a target price of $145,000, a ceiling price of $160,000, and a share ratio of 80/20. The actual cost of the project was $150,000. How much profit does the seller make?

  1. $10,000
  2. $15,000
  3. $0
  4. $5,000

16. Under what circumstances is it better for a contractor to subcontract?

  1. The subcontractor possesses special technical and engineering skills that the contractor does not have.
  2. The work to be subcontracted represents almost all of the overall work effort.
  3. The subcontractor can perform the work at a lower cost than the contractor.
  4. all the above
  5. a and c

17. Which type of bilateral contract is used for high dollar, standard items?

  1. Purchase order
  2. Request for proposal (RFP)
  3. Invitation for bid (IFB)
  4. Request for quotation (RFQ)
  5. all of them are appropriate

18. Which of the following are characteristics of a purchase order?

  1. A bilateral contract used for low dollar items
  2. A unilateral contract used when routine, standard cost items are required.
  3. A bilateral contract used for high dollar, standard items
  4. a and c

19. In which stage of the negotiation meeting are points of concession identified?

  1. probing
  2. closure
  3. agreement
  4. scratch bargaining

20. Which type of warranty is enacted if a service or product does not meet the level of quality specified in the contract?

  1. Implied warranty of merchantability
  2. Implied warranty of specified quality
  3. Express warranty
  4. none of the above

Answers

  1. c
  2. e
  3. a (particulary if buyer wishes to exercise some degree of influence or control over subcontracting decisions)
  4. d
  5. e
  6. a
  7. e
  8. d (proposals is the other input. procurement documents are input into the Solicitation Process)
  9. d
  10. e
  11. d
  12. d
  13. a
  14. b
  15. a is implied
  16. e
  17. c
  18. b
  19. d
  20. c