The review for the specification completeness is performed during which of the following cycles.

Requisition cycle (not award)

>>>>

The schedule risk is the _____Critical Path adjusted by "high-risk" activity float.

>>>>>>>

Acquisition is not a method of government procurement. (seal bidding, competitive proposals, assistance ,small purchases are)

>>>>>>>

The scope baseline/project charter is prepared by the:

Project manager, project sponsor and customer/user

>>>>>>>

Warranty cost is an example of an _____ .

External failure cost

>>>>

In crashing a task, you would focus on:

Accelerating performance of tasks on critical path. (not non critical path)

>>>>

Work authorization forms are needed in order to:

Authorize line organizations to charge against the project, establish an audit trail, Develop a structured methodology for release of funds

>>>>>The five major cost categories of quality are _____ .

prevention, appraisal, internal failures, external failures, and equipment (measurement and test).

>>>>The formalization of management's attitude toward risk is called _____utility theory (not sensitivity analysis, decision theory, decision tree analysis/probability)

>>>>>>

The range of time allowed for an activity to be completed in is the _____.

Scheduled time (LF - ES)., (Float time (LS - ES, or LF - EF) ; Critical time (when ES = LS, or EF = LF).)

>>>>>

A(n) _____ is defined as a specified accomplishment in a particular instant in time which does not consume time or resources.

Event (not activity)

>>>>

Attributes quality data are:

quality data for which the products or services is designed and built.,  quantitative & qualitative data, (not reflect measurements on a continuous scale of a characteristic of the product or service)

>>>>>>

Variables quality data are:

quality data for which the product or service is designed and built, reflect measurements on a continuous scale of a characteristic of the produce or service.

>>>>

Cost forecasting calculations include:

EAC = ACWP + (BAC - BCWP). , EAC = BAC/CPI

>>>>>

The core function of the PM is

Project integration (not client interfacing , quality assurance, personal administration)

>>>>

Which theory(s) prescribes a form of participative management?

Theory Y (not theory z/X)

>>>

Forecasting human resource requirements necessitates making predictions about both the supply and demand of human resources. Which of the following is not a method used to forecast the demand for human resources?

PERT CHART( Instead dephi method, Regression/Time series Analysis, staffing table)

>>>>

In crashing a task, you would focus on:

Accelerating performance of tasks on critical path.

>>>>

Arbitration is a _____ approach to conflict management in resolving conflict disputes.

Lose-lose

>>>>

Core Processes – Clear dependencies & same order

DC AFO – Definitive (5%),Capital Cost(10-15%) , Appropriate(15-25%), Feasibility(25-35%) , Order Of Magnitude(>35%)

Information gathering techniques  for Risk Identification – Delphi Techniques, SWOT Analysis , Brainstorming

OUTPUT of Solicitation Planning -  Evaluation Criteria, Procurement Documents, Statement of work updates

COMMUNICATION – is a knowledge areas that form parts of Project Closure

A quality audit is to identify lessons learned that can improve performance of this project

 

Communication planning is most tightly linked with what process: Organizational Planning

 

Which equation correctly illustrates the cost variance of a project, in cunency?

BCWP-ACWP      PMBOK Figure 10-3, 10.3.2.4   

 

The percentage of cost variance of your project is BCWP/ACWP

 

The two phases used in Project Cost Management are:  Controlling & Planning

 

Parametric Modeling and Analogous Estimating are used in what process: Cost Estimating Tools and Techniques

 

A tool or technique for cost control?

Cost change control system

Performance measurement

Additional planning

 

Human Resource Management is a knowledge area that  involves organizational theory as a tool/technique?

 

Cost Budgeting is defined as: Allocating the cost estimates to the individual work items

 

The cost baseline is an output of what process?  Cost budgeting

 

The primary conmunication skills you will use in working with your project sponsor will be: problem solving  & team building with project team members & NEGOTIATION with functional managers

 

Example of project integration management:

At project closure you transition the project operations into ongoing operations

Insuring that the product scope and the project scope are consistent.

A change in the project scope necessitates changes to the schedule and the budget.   PMBOK 4

 

Configuration Management, Performance Measurement and Project Management Information Systems are all: Tools and techniques used in overall change control

 

A  tool or technique for overall change control – Performance measurement, configuration management, Project management info sys.

 

A tool / technique for project plan exec – work authorization sys,general mgmt skills, product knowledge & skills

 

Meredith & Mantel describe four varieties of project termination - Termination by Extinction,Integration , Starvation

 

"To Complete Performance Index" (TCPI) is calculated by: Dividing the budgeted cost of the remaining work by the difference between the estimate at completion and actual costs to date

 

A management control that rarely changes, and then only in response to defined criteria, such as a change in scope is called a: Project baseline

 

Input into solicitation planning are Procurement management plan, Statement work, Project Schedule

 

A make or buy analysis is used as: A technique for procurement planning

Techniques for Source Selection- Weighting & Screening system, Independent estimates

 

Outputs from the Initiation process include: Project Charter, assumptions, constraints PMBOK 5.1.3

 

Product documentation is input to what process  scope verification

 

Tools  & Techniques establishing the schedule baseline.: Duration compression, Resource Leveling Heuristics, PERT

 

PMBOK 5.2.3.1    Project charter -> Scope statement , scope definition

 

Scoring models, comparative approaches and benefit contribution are all part of

Benefit measurement models for selecting a project

 

Scope verification is a part of : Project Execution

 

output of scope change control? Scope changes, corrective action, lesson learned

input of scope change control – Performance Report    PMBOK 5.5

 

Work Breakdown structure : It is a deliverable oriented grouping of project element.1

 

The document that describes the project's scope baseline is:

Work breakdown structure

 

The two closing procedures are called: Contract close out and administrative closure

 

A work package is:a deliverable at the lowest level of the Work Breakdown Structure

 

Overall change control is concerned with Determining that a change has occurred, Managing changes as they occur, creating change request

 

input to overall change control : performance report, change request ,project plan

 

a standard inclusion in a change control system? The responsibilities of the change control board, How to handle changes in emergencies, Procedures to handle changes that may be approved without prior review

 

a part of the controlling process? Schedule & cost

 

Document the change order and buy blue paint PMBOK 4.3

 

input to the information distribution process? Work results

 

 

 

 

 

 

>>>>>>>

Justification: Please refer to Transference
PMBOK 2000 Page 142
PMPExamPrep note: If the design is unstable, there is a potential that the seller also will not be deliver to specifications. Hence there is a risk that the project will not succeed, and both the seller and buyer will be impacted. Fixed Price contract for transference of risk is only effective if the project design is stable

 

>>>

In a Normal Distribution, the PERT duration (also called mean) = (Pessimistic + 4* (Most Likely) + Optimistic)/6
= (10 + 4 * 13 + 16)/6
= 13

1 Standard Deviation (sigma) = (Pessimistic - Optimistic) / 6
= (16 - 10) / 6
= 1
Mean - 6 sigma = 13 - 6* 1 = 7
Mean + 6 sigma = 13 + 6* 1 = 19

So, if the the company has a quality requirement of 6 sigma, then the task can be completed within 7 days to 19 days.

To know more about 6 sigma calculations, please refer to

>>>>>

an output from the Contract Closeout process? Contract File

>>

Corrective Action is an output of Integrated Change Control and not a "Tool".

 

>>

In schedule development, you create a distribution of probable results for each activity and use it to calculate distribution of probable results for the total project. The technique that you are using is: Monte Carlo Analysis

Simulation involves calculating multiple project durations with different sets of activity assumptions.

<>>>>

Proposals are an output from Solicitation . All the following are outputs from Solicitation Planning  Procurement Documents, Evaluation Criteria, Statement of Work Updates

>>>>

Product documentation refers to the documents produced to describe the projects products - it includes plans, drawings and specifications.

>>>

Risks and Triggers are outputs of: Risk Identification

>>>

Output of the Scope Initiation Process? Project Manager Identified, project charter , assumptions & constraints

(scope mgmt plan is not one of the output)

>>>>

All the following are examples of Constrained Optimization : Logical Framework Analysis, Multi Objective Programming, Decision Trees.  Economic Models are part of Benefit Measurement methods.

>>>>

Mathematical Models are used as part of Parametric Modeling

true about Analogous Estimating: Also called top-down estimating,  Used to estimate total project costs without detailed information about project., Actual cost of a previous small project is used for creating estimates

>>>>

parametric cost estimating  techniques  uses the statistics model .

>>>

0.2 of the extra costs of the project can often be attributed to a lack of quality. (not 0.25/1)

>>>>

A budget estimate should give the manager cost data accurate to within: -10 to +25 percent of actual cost

 

>>>

The two types of parametric estimates are Regression analysis & Learning Curves

>>>>

One common way to compute EAC is to take the BAC and Divide by CPI

>>>>

The Work Breakdown Structure (WBS) is the basis for communicating:

Project scope, cost control, schedule, quality

>>>>

Risk event probability is defined as:

The total number of possible events divided into the expectations or frequency of the risk event

>>>>

Scheduling systems such as PERT, ADM, and PDM are project management tools to be used by:

The project manager and project office personnel, project team & functional manager.

>>>

A process characteristic has a true mean of 150 and a true standard deviation of 20. A sample of 25 items is taken from this process. The standard error of the estimate is:4

>>>

Developing alternative activity sequences is an example of:

Contingency planning

>>>

To be able to be relied on in the rest of the risk management process, the risks identified for the project, it would be MOST important to complete which of the following? Data precision ranking

>>>>

Qualitative risk analysis is part of the risk management process uses data precision as an input

>>>

Two people are in the process of estimating probabilities for each of their identified risks. Which step of risk management is this? Risk quantification

>>>>

What are the tools and Techniques for Project Plan Development?

Project Planning methodologies, Stakeholder's Skills, PMIS and Earned Value Management

>>>>

 

A process characteristic has a true mean of 150 and a true standard deviation of 20. A sample of 25 items is taken from this process. The standard error of the estimate is:

The standard error is standard deviation divided by square root of the sample. For this example, it's 20/5=4. 

Opinion: The margin of error in a sample of size n is 1/sqr(n). So, in this question the margin of error = 1/sqrt(25)=0.2. The value of mean and standard deviation is irrelevant for this question.
Counter-Opinion: It asks about the standard error not the margin of error.

>>>>

(Sequence of administrative closure: acceptance of product, completion of lessons learned, archive records & release resources)

>>>

The knowlege area that comes into play when a cost estimate is needed for a contingency plan is Project integration management   PMBOK p41 Chap 4: (b) the others are red herrings

>>>

What value does the WBS provide to the project?

- Responsibility Assignments can be made to each task

- Estimated Costs can be developed accurately

- Entire project can be portrayed

- Objectives can be linked to resources

- Provides basis for the scope of project

>>>

The future value of $3000 invested for 5 years at 12 interest is:

$ 5,287.00    FV=PV(1+r)^t

>>>>

A control chart shows that the last eight pipes produced were all less than average weight. You need to inform management that there is a problem because the situation violates the:

rule of seven.

>>>>>

Amount at Stake is the  cost of investment loss + least cost to restore status quo.

>>>>>

In which of the following is the cost of risk hidden by the contractor?

Cost Plus Percentage of Cost

>>>

The cost of a quality program should be budgeted at __3.5%___ of the total project.

>>>

 

Which of the following control types has the highest risk to the owner:

Time and material (T&M)  & TO THE CONTRACTOR IS  Firm fixed price (FFP)

>>>

a method used to forecast the demand for human resources? Delphi Method, Regression Analysis, staffing table, Time Series Analysis

>>>>

The formalization of management's attitude toward risk is called _____ .

Utility Theory

>>>>

The most frequently used construct in Precedent Diagramming Method is: Finish to start

>>>
The specification for a particular part is 10" + or - 0.015". The standard associated process produces parts with a means of 10" and standard deviation of 0.002'. The process capability index is: 2.5

>>>

Which of the following is indicative of negative float?

The late start date is earlier than the early start date.

>>>>

Line of balance charts are used most frequently in:

 Manufacturing

>>>>

Project tradeoffs are usually made by comparing _____ and constraints.

Cost, quality & technical performance

>>>

Standard "Shewhart" control charts assume that the distribution of sample means is:

Normal & symmetrical

>>>

Risk exposure refers to _____the amount at stake

>>>

A quality control manager decides to increase his daily sample size from three to six. The size of the control band will:

- Decrease

>>>

Risk mitigation is the process of _____ .

reducing uncertainty on the project

>>>

A quality control manager decides to increase his daily sample size from three to six. The size of the control band will:

Decrease (not increase)

>>>

Control charts can be used to establish as well as maintain process control

>>>

Cost forecasting calculations include:

EAC = ACWP + (BAC - BCWP)

EAC = BAC/CPI

>>>>

team members are more likely to be assigned to the project office in a strong matrix

>>>>

The functional organization is effective with a mature product or single product line.

True

>>>

Considering alternate suppliers is a form of _____.

Value engineering

>>>

Which of the following organizations has the best technical project control?

Technical & Projectized

>>>

The estimated cost to complete (ETC) is _____.

the forecasted and final cost - cost to date

>>>>

The ability to achieve cost savings is inversely proportional to _____.

the earned value achieved to date

>>>

Which of the following is based on an individual identification with a more powerful person.

Referent power

>>>

The role of the _____ can be invaluable in problem solving.

Devil advocate

>>>

Which of the following are types of status reports?

 

cost, schedule, technical performance

>>>>

Using "I" or "My' instead of "most people" or "our group" ______ message credibility.

Increase

>>>>

Which of the following can be tracked using the WBS?

Scope

>>>

 

Which type of contract provides the highest risk to the Owner (Buyer)?

Cost Plus Percentage of Cost

>>>>

In negotiations, what is a fait accompli tactic?

Claiming an issue has already been decided on and cannot be changed

>>>

In general, product specifications are best developed by __________.

Technical staff

>>>

Allocating human resources is most straightforward in what type of organization?

Functional

>>>

In general, if a division's activities are focused on the achievement of a single major project, what is the way for it to structure its operation?

Functional structure

>>>

Constrained optimization methods of project selection include:

Scoring method

>>>

In typical project situations, who among the following has the smallest role to play in selecting projects?

Purchasing expert

>>>

The project __________ prescribes the guidelines within which a project is organized, administered, and managed for the timely accomplishment of project objectives.

Management plan NOT charter

>>

Selection of an organization to prosecute a project depends upon three key items: degree of advanced technology in the project, percentage of project personnel in the professional category, and the __________ for the project.

Level of uncertainty

>>>

A summary activity in a network logic diagram is often referred to as a  HAMMOCK

>>>

A request for proposal (RFP) is used to:

solicit bids from contractors/ 

maintain control over unauthorized work changes (wh is correct? CT2005_Q103)

>>>

Constrained optimization methods of project selection include:

Scoring methods  not ‘benefit-cost’ ratio,…etc

>>>

A summary activity in a network logic diagram is often referred to as a

Hammock

>>>

Change control requests:

Are inputs to integrated change control

>>>

Work-authorization system_________ is the formal procedure for sanctioning project work to ensure it is done at the right time.

>>>

Which method does not use boxes or nodes to represent work or activities?

ADM (PERT,PDM & GERT does use it)

>>>

Which is a tool or technique of the schedule development process?

Duration compression

>>>

Which type of cost estimate is based on individual activities?

Bottom up (not analogous/parametric)

>>

Using the chart below, what is the cost variance?
PV=$10,000
EV=$12,000
AC=$15,000

Answer: -3000 (PMBOK 2000 - PG 123)

>>>

Which is not a part of the cost budgeting process? Resource requirement ,(project schedule, cost estimates, WBS are ) PMBOK 2000 – PG 89

>>>

Earned Value is: budgeted value of work actually accomplished (PMBOK 2000 – PG 123)

>>>

The future value of $3000 invested for 5 years at 12 interest is: 5287

FV = PV(1+R) (Superscript "n") where PV is present value, R is int rate, n is num yr

>>>

Which of the following is not part of the quality assurance process?

Quality policy ( quality audits/improvement,operational definitions)

>>>

A packing process results a product with a mean weight of 8 ounces. The process has a standard deviation of 0.5 ounce. What percentage of samples will weigh between 7.5 and 8 ounces? 34.13

--One STD , 68.3% of samples Two STD , 95.5% of samples Three STD, 99.7% of samples One STD for this question would range from 7.5 to 8.5. Question asks for 7.5 to 8, assuming ½ the deviations are over and ½ are under the answer would then be half the deviation percentile or 34.13%

>>>>

Which of the following is a primary motivational tool of McGregor’s Theory X?

Safety

>>>

Which of the following is not part of a modern quality management concept?

A.

Performance standard is zero defects

B.

Quality must be inspected in  (answer)XXXX

C.

85% of failures occur because of the process, not the worker

D.

Quality is a 4 cycle process – plan/do/check/act

A IS CROSBY’S THEORY, C IS TAGUCHI THEORY, D IS DEMING THEORY. Quality is designed not inspected into a product is part of Taguchi theory.

>>>

Which of the following is an input to the team development process?  External Feedback

PMBOK 2000 – PG 108

>>>>>>

Which theory specifies money as an important employee motivator?

Theory X Mcgregor

>>>

the information distribution process? Project plan, project  records , communication skills

>>>

Risk response planning is one of the _______________ processes

planning facilitating processes

>>>>

Estimated at Completion is determined by:

ETC + ACWP  ,  BAC/CPI

>>>

Parametric cost estimating involves:

Using rates and factors based on historical experience to estimate costs

>>>>

A cost management plan is: A plan for describing how cost variances will be managed

>>>>

Cost estimating:  Involves developing an estimate of the costs of the resources needed to complete project activities,

Includes identifying and considering various costing alternatives

>>>>

CT2005  180-183

>>>

A histogram ordered by frequency of occurrence that shows how many results were generated by each identified cause is:

Pareto Diagram

>>>>

The practice of ceasing mass inspections and ending awards based on price is credited to:

Edward Deming

>>>>

The concept that it is easier and less costly to do the work right the first time is called: DTRTRTFT

>>>>

What percentage of sales is estimated to be the cost of non-quality?

12-20%

>>>>

A series of consecutive points on the same side of the average is called:

Run

>>>

80% of the problems are found in 20% of the work is a concept of:

-Pareto

>>>

The input to organizational planning consists of

Project interfaces, staffing requirements, and constraints

>>>

outputs of Organizational Planning:- Project organization charg, staffing management plan, project template, supporting detail

>>>>

A project manager who has a low concern for personal goals and a high concern for relationships is practicing which style of conflict resolution?

Yield – Lose

>>>

A key component of concurrent engineering is

Involving the implementors of a project in the design phase

>>>>

The three types of power available to the project manager based solely on his or her position in the organization include

Formal, reward, penalty

>>>>

In both the weak and strong matrix organizatoinal structures, the primary condition leading to conflict is

Ambiguous jurisdictions

>>>>

The chances for succesful completion of a multidisciplinary project are increased if project team members are

Problem oriented

>>>>

The terms strong matrix and weak matrix when applied to the matrix structure in project organization refer to the

Degree of authority the project manage has over team resources

>>>

The key to achieving and maintaining success in the role of a project manager is the use of

Reward & expert power

>>>>

When appointed, a project manager has the inherent forms of legitimate power conveyed to him/her. The three forms of legitimate power are ________.

formal, reward, and penalty

>>>>>

two forms of power that are obtained through other than a formal appointment (legitimate power). These two forms of power are ________. expert and referent

>>>>>

There is a long-term need to develop individuals within a company to assume positions of leadership and greater responsibility. Comparing the functional and project organization, the opportunity for personnel development ________.

-is greater in the project organization

>>>

A mandatory prerequisite for team building is

A commitment from top level mgmt

>>>

Project Human Resource Management is divided into

Organizational planning, staff acquisition, and team development

>>>

A chart that shows the level of all project resources by time period is known as a

Resource Spreadsheet

>>>

Adjusting the timing of tasks so that resources are not over committed is called

Resource Levelling

>>>

What are Maslow's three highest levels of human needs?

Self-actualization, esteem, and social

>>>

A project is considered closed when the:

Archives are completed (not when contract finish/client accept products)

>>>

What is the LAST thing to do in project closure?

Release the team  (not update archives)

>>>>

The project is completed and the final deliverable has been sent to the customer, but the customer refuses to give final acceptance on the project. It is MOST important for the project manager to:

Document the situation

<<<

What is the BEST technique to ensure proper contract closure?

Procurement audits

>>> (if contract closes, then procurement audit found some problem, project still consider complete)

>>>>

Scope verification IS NOT PART of Administrative closure

>>>

Which of the following is a common problem in administrative closure?

Retaining resources to complete the project

>>>

Administrative closure is different than contract closure in that:

contract closure includes an audit while administrative closure does not.

>>>

Which of the following regarding performance reporting is correct?

It is done during control and closure. (not execution/planning  & control)

>>>

A seller has failed to make delivery on a major item for your project. What should you do?

Have the contracting officer terminate the contract for default

>>>

CT_2004 (lots of CLOSURE contracts, communication ques..)

>>>

When a seller breaches a contract, the buyer cannot receive

Punitive damages  ( check Mr.dic what’s arbitrary?- neutral party to solve contract termination problem)

>>>

Which item is NOT a basic element of a contract?

Pricing structure (offer, acceptance, consideration)

>>>

During solicitation planning, the project team is responsible for

Developing the procurement documents

>>>>

Which term describes those costs that are associated with two or more projects but are not traceable to each of them individually?

Indirect ( not fixed, direct , variable)

>>>>

A purchase order is a good example of which form of contracting?

Unilateral (not bilateral/trilateral. severable)

>>>

Requirements for inspection and acceptance are defined in the

Contract (not procurement plan)

>>>

What is the BEST technique to ensure proper contract closure?

Procurement audits ( not formal acceptance)

>>>

All of the following are part of administrative closure EXCEPT?

Scope Verification (the rest are update empl. Skills, record reasons for termination, transfer info from one phase to another)

>>>

A project team has completed all the technical project deliverables, and the customer has accepted the deliverables. However, the lessons learned required by the project office have not been completed. What is the status of the project?

The project is incomplete until all deliverables are complete and accepted.

>>>

Closure includes all the of the following EXCEPT:

determining performance measures. (include only appraisal review of team, documenting the degree to which each project phase was properly closed after its completion. / documenting final project scope)

>>>

A buyer has negotiated a fixed-price incentive contract with the seller. The contract has a target cost of $200K, a target profit of $30K, and a target price of $230K. The buyer has also negotiated a ceiling price of $270K and a share ratio of 70/30. If the seller completes the contract with actual costs of $170K, how much profit will the buyer pay the seller?

39K ??? how to derive??

>>>

Scoring models, comparative approaches and benefit contribution are all part of:

Benefit measurement models for selecting a project (PMBOK 5.1.2.1)

>>>

During the schedule development process the Project Manager may have to go through several iterations of the schedule before establishing the schedule baseline. All of the following are tools and techniques that may be used during this process:

Duration compression, Resource Leveling Heuristics, PERT

>>>

The "To Complete Performance Index" (TCPI) is calculated by:

Dividing the budgeted cost of the remaining work by the difference between the estimate at completion and actual costs to date

>>>>

The amount of time that an activity can be delayed from its early start without delaying the project end date is called:

TOTAL FLOAT & FLOAT

(Free float is the amount of time an activity can be delayed without affecting the start time of the succeeding activity )

>>>

What are you likely to see as a project progresses in a schedule with must fix dates and little or no slack?

Negative Float

>>>In crashing the schedule, you would focus on:

Accelerating the performance of tasks on the critical path

>>>>

To calculate the late start and late finish dates for a set of tasks, you must do:

A backwards pass (not a forward pass/ analysis of the critical path)

>>>>>>

A network diagram that uses nodes to represent activities and arrows to show the activity dependencies and allows no loops is called:

AON

>>>>

Which of the following choices indicates that a project has a burn rate of 1.2? Hint: Burn rate is the same as the Cost Performance Index

CPI=BCWP/ACWP=1.2 This means that for every dollar spent, the project is acheiving $1.20 of value

>>>>

The inputs to Cost Budgeting includes all of the following except:

Cost baselines are outputs to Cost Budgeting & input to Cost Control  ( input-cost estimates, WBS , Project Schedule)

>>>>

Estimated at Completion is determined by:

ETC + ACWP   &  BAC/CPI

>>>

During what Time Management Process are the specific activities that must be performed to produce the deliverables in the WBS identified and documented?

Activity Definition

>>>>

Parametric cost estimating involves:

Using rates and factors based on historical experience to estimate costs

>>>>

A cost management plan is:  a plan for describing how cost variance will be managed?

>>>>

The process of evaluating overall project performance on a regular basis to provide confidence that the project will satisfy the relevant quality standards is called:

Quality Assurance ( not quality control / planning/ review)

>>>>

 

A histogram ordered by frequency of occurrence that shows how many results were generated by each identified cause is:

Pareto Diagram ( Statistical / Juran / Fishbone diagram)

>>>>

Tools and techniques used during the Quality Planning process include:

Benefit/Cost Analysis , Bench Marking  ( not Quality audits as it’s used during Quality Assurance)

>>>

The practice of ceasing mass inspections and ending awards based on price is credited to: Edward Deming ( not Philip Crosby, Juran, pareto)

>>>

What percentage of sales is estimated to be the cost of non-quality?   12-20%

>>>

A series of consecutive points on the same side of the average is called:  RUN

>>>

A tool that analyzes the inputs to a process to identify the causes of errors is called:

Cause and effect diagram   &   Ishikawa Diagram

>>>>

process of project human resource management? Organization planning, team development, Staff Acquisition

>>>

Recruitment practices is an input of Staff Acquisition not an input into organizational planning?

Organizational planning INPUT are project interfaces, staffing requirement, constraints.

>>>

When should the project expeditor form of organization be used?

When a project's cost and importance are relatively low

>>>

The belief that management's high levels of trust, confidence and commitment to workers leads to high levels of motivation and productivity on the part of workers is a part of which motivation theory?   THEORY Z

>>>

 

The staffing management plan often includes resource histograms, A document or tool which describes when and how human resources will be brought onto and taken off the project team

>>>

A tool which links the project roles and responsibilities to the project scope definition is called:

Responsibility Assignment Matrix

>>>>

Decoding is deciphering a message once assimilated ; In communications management, to assimilate through the mind or senses is the process of:  RECEIVING

>>>

The three major types of communication are:

Written, verbal, and non-verbal (it’s not electronic/graphics)

>>>>>

The outputs of performance reporting are change requests and performance reports. Stakeholder reports are examples of performance reports and B are examples of the formats for performance reports (S curves, histogram, bar chart & tables)  :: Trend Analysis is NOT output

>>>

A tight matrix is:   Where all team members are brought together in one location

>>>

 

What are the four parts of the communications model?

Sender, Message, Medium, Receiver

>>>>

A leadership style in which the project manager shares problems with team members and formulates solutions as a group is called:   CONSENSUS

>>>

 

A type of organization in which the project manager has little formal authority and basically acts as a staff assistant to an executive who is ultimately responsible for the project is called:

Project expediter (not project coordinator)

>>>>

In which of the following organizations is the project manager role likely to be part-time? Balanced Matrix

>>>>

Management reserves are used to handle which type of risk?

Unknown unknowns

>>>

Which of the following techniques accounts for path convergence and generally estimates project durations more accurately?

Schedule simulation (not path convergence method, PERT, CPM)

>>>>

Most schedule simulations are based on some form of which of the following?

Monte Carlo Analysis

>>>>

 

The independence of two events in which the occurrence of one is not related to the occurrence of the other is called:

Statistical independent ( not probability independent)

>>>>

The one document that should always be used to help identify risk is the:  WBS

>>>

Which of the following processes involves obtaining information (bids and proposals. from prospective sellers?  Solicitation (not solicitation planning, procurement planning)

>>>>

Which of the following is a method for quantifying qualitative data in order to minimize the effect of personal prejudice on source selection?

 Weighted system ( not screening system, selecting system)

>>>>

Which of the following are inputs to the Source Selection Process?

Evaluation criteria , organizational policies (Proposals is the other input. Procurement documents are input into the Solicitation Process )

>>>

A significant difference between independent estimates and proposed pricing could mean that:

The SOW was not adequate,  The prospective seller either misunderstood or failed to respond fully to the SOW

>>>>

 

RULE OF SEVEN ????

>>>

The major project scope management processes include: initiation(not change control/scope validation/program evaluation)

>>>>>

An input to the scope change control process is:  performance reports (not customer requirement/ product defects/ work results)

>>>>

Developing a written scope statement as the basis for future project decisions is called:

Scope planning (not scope definition, product analysis, project development)

>>>>

Techniques for conducting product analysis include:

 Value engineering ( not technical benefit analysis, expert judgement, alternatives identification)

>>>>

Scope planning includes alternatives identification, which can be conducted by the common technique of:   Lateral thinking (not value engineering)

>>>>

A project management professional can compare earned value performance data to all of the following project management tools EXCEPT:  forecast final cost/estimates

(should include Critical path analysis,  Technical performance metrics, mitigation plans)

>>>

core planning processes are: Scope Planning, Scope Definition, Activity Definition, Activity Sequencing, Activity Duration Estimating, Schedule Development, Resource Planning, Cost Estimating, Cost Budgeting, Project Plan Development   ::: Comm. Planning is OUT

>>>

PMBOK HR Mgmt, pg 99-101." Team development includes both enhancing the ability of stakeholders to contribute as individuals as well as enhancing the ability of the team to function as a team. Individual development (managerial and technical) is the foundation necessary to develop the team. Development as a team is critical to the project's ability to meet its objectives." Difference between Team Devt and team Building - PMBOK pg 99 section 9.3 Team Development is a process on the HR Mgmt knowledge area. Team Building is a tools & Technique for the process (pg 100)

>>>>>>>>>

Which of the following Project Scope Management processes involves subdividing the major project deliverables into smaller, more manageable components?

Scope definition (not scope planning)

>>>>

In which type of organization(s) is the project manager's role most likely part-time?

Functional & Weak Matrix

>>>

 

  Management reserves are used to handle which type of risk?

Unknowns-unknowns , but contingency reserves is handle risk type of knowns-unknowns

>>>

Which of the following is true about procurement documents?

Procurement documents are used to solicit proposals from prospective sellers

Procurement documents should be structured to facilitate accurate and complete responses from prospective sellers

Invitation for Bid and Request for Proposal are two examples of procurement documents                      

>>>>

Scope planning is:

Developing a written scope statement as the basis for future project decisions

(not Subdividing the project into smaller, more manageable components)

>>>>

All of the following are tools for scope verification EXCEPT?

Sensitivity analysis (audit,walk through, product reviews are)

>>>>

An advantage of a fixed price contract is:

 Cost risk is lower

>>>>

Maslow – self esteem

Herzberg – hygiene factor

Mcgregor – employee theory X,Y

Deming -  quality stop mass inspection

>>>>

Standard deviation is a measure of how: far the measurement is from the mean.

>>>>>

During the source selection process of procurement, your objective is to obtain the best price possible. The tool that you will MOST heavily rely upon will be a(n):

independent estimate. (not weighting/ screening system)

>>>>

 

Which of the following is an example of the cost of conformance to quality?

Quality training ( not  Rework, Scrap, Warranty costs ???)

>>>>

What theory proposes that efforts will lead to effective performance and will be rewarded for accomplishments?  Expectancy Theory ( not Mcgregor)

>>>

Which of the following is the highest point in Maslow's hierarchy of needs?  Esteem

>>>

During what step in the procurement process does contract negotiation occur?

Source selection ( not procurement/solicitation planning, solicitation)

>>>

You are asked to prepare a budget for completing a project that was started last year and then shelved for six months. All the following would be included in the budget EXCEPT?

Sunk cost ( the rest are included eg. fixed/variable/ Direct cost)

>>>

Which of the following MUST be an agenda item at all team meetings?

Discussion of project risks ( not status of tasks/ review of project problems)

>>>

You are managing a project where your team is physically located with client personnel at a remote location. There is a high level of interaction between your team and client personnel, and client satisfaction is considered very important. Since the client is expressing a very high level of satisfaction with the project's progress, your management has indicated no concerns about the project. However, you are behind schedule and over budget. In addition, morale among team members is low, and several have talked about quitting. Team members complain regularly about priority adjustments and alteration of tasks. The weekly reports you receive about activities completed are often difficult to relate to the WBS and the project plan. What action should you take to MOST effectively address these problems?

You should enforce scope change control. (not motivate team??)

>>>>

Your project no longer ties into the company's objectives. What would be the BEST thing to do?  Increase the schedule (not decrease cost)

>>>

Which of the following is done during scope verification?

Inspection ( not create wbs, performance measurement,verify product correctness)

>>>>

Which planning output may be revised and refined as it moves through the procurement process?  Statement work ( not contract changes , proposal, procurement documents)

>>>

Which of the following is an advantage of centralized contracting?

Increases company expertise in contracting

>>>>

The "halo effect" refers to the tendency to:

move people into project management because they are good in their technical field.

>>>

The product of the project is created during:

project plan execution. (not project plan development/ schedule dvlpm, integrated change control)

>>>  **IL_* test prep mostly on procurement ques??

The party that needs the change resulting from the project, and who will be its custodian on completion is the  Owner (not sponsor?-another prep say is, not customer/client)

>>>

 

Critical input to scope initiation is:

Project charter

>>>

Crosby's Four Absolutes of Quality Management:
1.What is quality? Quality is conformance to requirements, not goodness.
2.What system is needed to cause quality? Prevention, not detection.
3.What performance standard should be used? Zero-defects, not "that's close enough".
4.What measurement system is required? Price of conformance andnon-conformance.

>>>>

To make an informed decision about buying insurance, the project manager needs to determine the ratio of insurance cost and the expected value of the loss. For example, if the cost of insurance is $10,000, the value of the property is $200,000, and the probability of loss is 0.05 (or five percent) the insurance is ________.

--the same as the cost of the probable loss and there is no advantage

(The EMV is 5% x 200,000 = 10,000 same like the insurance cost )

>>>>>

The single point standard deviations are 3, 5, 10 and 3 for the critical path. What is the standard deviation for the entire path?

12 --- The total path standard deviation is calculated by the square root of the sum of the squares of the activity standard deviations>

>>>>

Using the situation below and assuming continued efficiency for work-in progress and fixed price contract for task four.

Task

Budgeted Cost

BCWS

ACWP

BCWP

Task One

$5K

$5K

$6K

$5K

Task Two

$6K

$6K

$8K

$4K

Task Three

$4K

$2K

$1K

$1K

Task Four

$4K

$0K

$0K

$0K

The estimate at completion is:26K

(think formula is Budgeted Cost/ CPI ie  BCWP/ACWP)
Explanation 2:
You should try this problem task wise, i.e. calculate each task separately so:
Task One = 5 / (5/6) = 6
Task Two = 6 / (4/8) = 12
Task Three = 4 / (1/1) = 4
Task Four = 4 (LumpSum)
Total = 26

>>>>

When should the project baseline be changed?

For all implemented changes (not by the control board)

>>>>

Which of the following represents information presented in its order of priority and helps focus on the MOST difficult issues?  Pareto chart

>>>>

What is the duration of a milestone? There is no duration

>>>

Which of the following BEST describes a risk owner?

The person who will be responsible for implementing the risk response strategy

>>>>

 

All of the following are part of the quality control process EXCEPT?

Bench Marking ( part of quality control process includes Trend analysis, control charts, Inspection)

>>>>

Which of the following would not be available during planning?

Cost performance Index CPI (only benefit cost ratio, internal rate of return, budget completion)

>>>>

The level of detail of performance reports is described in the:

Communication plan

>>>>

If EV is US $300,000, AC is US $350,000, and PV is US $375,000, what does the schedule performance index indicate?

You are only progressing at 80% of the rate originally planned

>>>>>

During the implementation of a contingency plan a team member notices that the plan worked only marginally. There were three similar contingency plans developed for other risks that have not yet happened. He should recommend which of the following?

A project change request ( not workaround)

>>>

Originally a project has seven activities: A, B, C, D, E, F, and G. A, B and D can start anytime. A takes three weeks, B takes five weeks, and D takes 11 weeks. A and B must be completed before C can start. C takes six weeks to complete. B, C, and D must be completed before E can start, and E takes two weeks. F can start as soon as C completes and has a duration of four weeks. G takes three weeks and cannot start until E is completed. F and G must be completed for the project to be completed. However, during project execution, a dependency was discovered between activity E and F. What is the BEST thing to do?

Redo Schedule development (not crashing)

>>>

The sponsor of the project you are managing asks you to compress the duration of the project. Which of the following is correct?

Fast tracking often results in rework, and crashing often results in increased cost.

>>>>>

The purpose of a fishbone diagram is to:

stimulate thinking, organize thoughts, and generate discussion.

>>>>

All of the following are part of an effective change control system EXCEPT?

Lesson learned (only procedures, meetings, standard for reports)

>>>>

The sponsor wants the project completed in 40 days. The CPI is 1.1, the project critical path duration is 38 days with a standard deviation of two days. What is the maximum project float?

4 days

>>>

Residual risks are risks that remain after risk response planning. Secondary risks are:

new risks created by the risk response strategies selected.

>>>>

outputs of scope change control

Scope changes, corrective action, lessons learned  EXCEPT change requests

>>>>

If two events cannot both occur in a single trial, they are:

Mutually exclusive ( not statistical independent )

>>>>

Pareto diagram, Sampling, WBS can be used as a quality control tool except Life cycle costing

>>>>

Which of the following is part of modern quality management?

Addressing both the project management and the product (not using the zero defects techniques)

>>>>

Originally a project had four team members. Now the scope has expanded, and there are a total of six people on the project team. How many communication channels does the project have? 15

>>>

There are four people on the project team, and the project manager adds three more. How many channels of communication are there now?  21

>>>

A project team is having difficulty communicating over long distances. There are 13 team members from two countries when five people from India are added to the project. How many communication channels are there? 153

>>>

If a project manager wants to report on the actual project results planned, he would use a:

Variance report ( status report, forecasting report, trend report)

>>>

Inputs to communications planning include communications requirements., technology available to transfer information., constraints, EXCEPT description of information to be distributed

>>>>

Project coordination is enhanced through progress reporting, variance reporting, and cross-team meetings. These are all forms of:  quality management (not communication management)

>>>>

The level of detail of performance reports is described in the:

Communication plans (not monthly requests for information by management./ project monthly needs)

>>>>

The project is completed and the final deliverable has been sent to the customer, but the customer refuses to give final acceptance on the project. It is MOST important for the project manager to:  document the situation ( not inform mgmt of the situation)

>>>

In their pure state, project reports are a method to:

Distribute information ( not report performance / plan communications)

>>>.

The purpose of status meetings is to:

exchange information about the project.( not have team members report on what they are doing, )

>>>

The project manager is working to clearly describe the level of involvement expected from everyone involved in the project in order to prevent rework, conflict and coordination problems. Which of the following BEST describes the project manager's efforts?

Integration management, control, communications planning

>>>

A contingency plan is

A planned response that defines the steps to be taken if an identified risk event should occur

A contingency reserve is A reserve used to allow for future situations which may be planned for only in part

>>>>>

Risk identification should be performed on a regular basis throughout the project(not during planning/development)

>>>>

The one document that should always be used to help identify risk is the:

WBS (not risk mgmt plan)

>>>

In summing probability distributions what is the formula for Mean?

 

Mean = (a + m + b) / 3

>>>>

In beta distributions using PERT approximations what is the formula for Variance?

Variance = [(b - a) / 6] 2

>>>>

When summing the probability distributions if the distributions are skewed to the __________, the project mean will always be significantly higher than the sum of the most likely estimates.

Left

>>>

U cannot eliminate project risks by doing the risk mgmt plan in project

>>>

Which phase of the project life cycle typically has the highest uncertainty and risk associated with it?  Concept (not development)

<>>>>

Total Project Risk

is the cumulative sum of the probability of each individual project risk event times the consequences of occurrence of that risk event

>>>>

Risk event probability is determined as:

The total number of possible events divided into the expectation or frequency of the risk event

>>>

Final risk quantification and modeling normally considers the impacts of all risks combined and:

Translated the impacts into economic terms for analysis  , May not consider safety and environmental impacts

>>>

Sensitivity Analysis can be used in risk analysis to:

Estimate the effect of change of one project variable on the overall project

>>>>

All of the following are outputs of scope change control EXCEPT?

Change Request (the outputs are Scope changes, corrective action ,lessons learned )

>>>

Quality control tools are Pareto, Sampling , WBS ( not life cycle costing)

>>>

 

 When should project baseline be changed? ????

>>>

If a project manager wants to report on the actual project results planned, he would use a:

Variance report

>>>>

The level of detail of performance reports is described in the:

Communication plan

>>>

The type of contract (payment mechanism) chosen for a project is of the degree of risk associated with completing that project. For a firm fixed price contract, payment for risks:

Is an undisclosed contingency in the contractor's bid

>>>

In Project Risk Management, Risk Response may include actions to:

reduce the probability of risk events; change the scope, budget, schedule, or quality specifications of the project;

reduce the consequences or severity of impacts of a potential risk event

>>>>>>>>

Graphical displays of accumulated costs and labor hours, plotted as a function of time, are called:  S Curve

>>>>

Project Mgmt / Project planning can address:

Intermediate range planning ( 1 to 5 yrs)  &

Short range/ tactical planning (1 yr or less)

>>>>

Preparation of the Scope baseline involves the:

Project Manager and project office, PM & Sponsor, Functional Team

>>>>

Mgmt. has decided to "crash" a project in order to avoid penalty payments for late deliveries. Additional costs are expected. To crash the project, either overtime or additional resources should be assigned to:

Those activities on the critical path beginning with the longest time duration activities.

( Is Not only for activities with the longest time durations)

>>>>

The major difference between PERT and CPM networks is:

PERT requires three time estimates, whereas CPM requires one time estimate.

>>>>

Once a logic of a network is laid out, the project manager will conduct a forward pass and then a backward pass thru the network. Doing this will provide information on the ___________ and identification of the _________.

Slack for each activity, critical path.

>>>>>

Assigning resources is an attempt to find the shortest project schedule consistent with fixed resource limits is called __________________.

Resource-constrained scheduling. (not resource leveling/partitioning/quantification)

>>>>

In the Arrow Diagramming Method (ADM), ________ do not consume time or resources.

Events  ( not Activities / Slack Elements)

>>>>

Among the common types of schedules are Gantt charts, milestone charts, line of balance, and : Networks ( not Time phased events/ calendar integrated activities)

>>>>

Which of the following is / are typical tools of statistical process control?

Pareto Analysis / Cause & Effect Analysis / Process Control Charts

>>>

The specification for a particular part is 10" 0.015". The associated process produces parts with the mean of 10" and a standard deviation of 0.002". The process capability index is:

 2.5

>>>>

Which of the following is / are part of the criteria by which a company is evaluated for the Malcolm Baldrige award?

Biz Result , Information Analysis, Leadership & Strategic planning

>>>>

Which of the quality gurus believed "Zero Defects " is achievable.

 Crosby ( what about Taguchi  ? Juran ? )

>>>>>>

A work breakdown structure is most useful for:

identifying individual tasks for a project, developing a cost estimate (not scheduling start of tasks/ determining potential delays)

>>>>>>>>>>

The primary consideration of product management is to know the _____.

functionality the product will provide over its useful life

>>>>>